Judgments

Search
R v C
CASE No: AIFC-C/CFI/2026/0019
20.08.2026
Judges
Sir Jack Beatson FBA
Summary
Following the dismissal of an application challenging the independence and impartiality of a sole arbitrator, the AIFC Court considered the issue of costs. The unsuccessful party argued that each side should bear its own costs because the challenge was brought to resolve legitimate concerns regarding the arbitrator’s impartiality. The Court rejected that argument, holding that the general rule requiring the unsuccessful party to pay the successful party’s costs should apply. After assessing the reasonableness and proportionality of the legal fees claimed, the Court ordered the applicant to pay KZT 4,250,000 in costs, representing 85% of the amount sought by the successful party.
SAMRUK SERVICE GROUP LLP v TETHYS AKTAU II LLP
CASE No: AIFC-C/SCC/2025/0063
10.08.2026
Judges
Josephine Higgs KC
Summary
Samruk Service Group LLP sought recovery of the final payment of KZT 8 million under a construction contract relating to the construction of a beach bar and related facilities at the Tetysblu theme park. The Defendant argued that the works contained defects and were not completed in accordance with the contractual specifications, and counterclaimed for a proportional reduction of the contract price. The AIFC Small Claims Court found that the Claimant had substantially performed the contract but that certain elements of the works did not comply with the agreed specifications or quality requirements. The Court held that the Defendant was entitled to a proportional reduction of the contract price in the amount of KZT 3.5 million and ordered payment of the remaining KZT 4.5 million, together with the court fee.
Judges
Josephine Higgs KC
Summary
iO Investments (Pty) Ltd brought a claim against Corundum Engineering LLC arising from a supply contract for goods. The Defendant admitted the contractual history and did not dispute the Claimant’s entitlement to payment for goods delivered under the contract. The AIFC Small Claims Court therefore ordered the Defendant to pay RUB 2,790,100. The Court declined to grant the requested declaratory relief regarding the delivery of goods and termination of contractual obligations because the proposed declarations were not sufficiently specified, while leaving the Claimant the opportunity to clarify and renew that request.
PRIVATE COMPANY “OCTOP S.A.A.” LTD v “HOLO MEDIA” LLP
CASE No: AIFC-C/SCC/2026/0011
31.07.2026
Judges
Josephine Higgs KC
Summary
OCTOP S.A.A. Ltd brought a claim against HOLO MEDIA LLP seeking payment for equipment supplied under a sale and purchase agreement. The Сlaimant demonstrated that the equipment had been delivered, the Defendant had failed to make the agreed instalment payments, and had subsequently acknowledged the outstanding debt in writing. The AIFC Small Claims Court determined the case on the papers, found that the Defendant had breached its payment obligations, and ordered it to pay KZT 29,304,239.70, including the contractual debt and accrued penalty.
CLAIMANT v DEFENDANT
CASE No: AIFC-C/CFI/2026/0029
29.07.2026
Judges
Tom Montagu-Smith КC
Summary
The Claimant challenged the impartiality and independence of an arbitrator under Article 22 of the AIFC Arbitration Regulations, alleging that the arbitrator’s academic affiliations, professional connections with members of the Defendant’s legal team, and several procedural decisions created a risk of bias. The AIFC Court admitted additional evidence but concluded that the alleged connections were remote, fell within the categories of professional relationships generally regarded as non-problematic under the IBA Guidelines, and did not require disclosure. The Court further held that the arbitrator’s procedural decisions reflected ordinary case management and provided no evidence of partiality. Accordingly, the challenge was dismissed, with costs to be determined separately.
Judges
The Lord Faulks KC
Summary
The claimant sought an order requiring the extension of the construction deadline for a public-private partnership hospital project by twelve months following the connection of all necessary utility networks. The Court found that the parties had reached a binding agreement, recorded in settlement meeting minutes, under which the commissioning period would be extended after completion of the external engineering infrastructure. Rejecting the defendant’s arguments that additional formalities were required, the Court granted the claimant’s request and confirmed that the project deadline should be extended as agreed.